ORLANDO, FL. – Construction activity at Orlando International Airport’s South Terminal Complex paused briefly in
recognition of the Independence Day holiday. Work will resume this Friday.
Progress is being made with crews working seven days-a-week to prepare the site for vertical construction in the fall.
So far:
Nearly 75% of the 4,000 total piles are in the ground
Two million cubic yards of dirt have been moved
Construction workforce has grown to more than 500 on site daily
The terminal scheduled for completion in 2021 will provide 19 new gates for domestic and international flights and
increase capacity to more than 50 million passengers annually at Florida’s busiest airport.
PAVIX: Proven Winner for All Airport Concrete Infrastructure
International Chem-Crete Corporation (ICC) manufactures and sells PAVIX, a unique line of crystalline waterproofing products that penetrate into the surface of cured concrete to fill and seal pores and capillary voids, creating a long lasting protective zone within the concrete substrate.
Once concrete is treated, water is prevented from penetrating through this protective zone and causing associated damage, such as freeze-thaw cracking, reinforcing steel corrosion, chloride ion penetration, and ASR related cracking.
This white paper discusses how the PAVIX CCC100 technology works and its applications.
Know of a project that should be covered in a future issue of Airport Improvement?
AIRPORT IMPROVEMENT is published bi-monthly by Chapel Road Communications LLC, 212 Cardwell Court, Napa, CA 94559. All statements, including product claims, are those of the person or organization making the statement or claim. The publisher does not adopt any such statement or claim as its own and any such statement or claim does not necessarily reflect the opinion of the publisher. Printed/published in the USA.
Send address changes to AIRPORT IMPROVEMENT to 212 Cardwell Court, Napa, CA 94559.
All rights reserved. Permission to reprint or quote excerpts granted only upon written request.