b'42 ATL TERMINALSFACTS&FIGURES Project: Terminal ExpansionLocation: Hartsfield-Jackson Atlanta Intl AirportConcourse: DAirport Owner/Operator:Atlanta Dept. of AviationProject Cost: $1.4 billionFunding: $40 million FAA Airport Terminals Program grant; passenger facility charges; airline rates & chargesScope: Widen concourse from 60 to 99 feet; extend length by 288 ft.; increase gate seating from 5,400 to 6,400Project Manager: Joint ventureof WSP, H.J. Russell & Companyand Turner & Townsend Architect: CorganConstruction Managerat Risk: Holder-Moody- Bryson-SovereignStart of Design Work:April 2022Start of Underground Utility Enabling Projects: Nov. 2023Module Construction Began:Jan. 20241 stModule Transport:April 24, 2024Expected Openingof Phase 1: Sept. 2024Anticipated ProjectCompletion: Summer 2029July | August 2024AirportImprovement.com'