Expansion. While many airports add space 
by expanding outward, SEA had to get 
creative. “We couldn’t build out, so we 
built up,” Reiter says. 
The joint design team of The Miller Hull 
Partnership and Woods Bagot stacked 
new public spaces vertically above the 
existing structure, creating an open, light-
filled space that now serves as the heart 
of the C and D concourses.
For Reiter, the project reflects a 
broader vision of the airport’s future. 
“This is truly what we wanted to see for 
SEA—a place where you feel at home 
and you get a feeling of space.”
A Place to Linger
Anchoring the center of the new space 
are the Grand Stairs and the Tree at C, a 
sculpted architectural element sheathed 
in locally sourced Western Hemlock that 
rises from the midpoint of the extra-wide 
staircase and connects physically and 
blends visually with the wood-veneer 
acoustic ceiling. (See photo above). The 
staircase is peppered with 15 illuminated 
boxes that feature various works by three 
Pacific Northwest artists. Together, the 
features encourage passengers to look 
up and explore the restaurants, gathering 
spaces and public lookout on the third floor. 
The 20-foot-tall Tree at C was a 
collaboration of architects Woods Bagot 
and The Miller Hull Partnership for design, 
Armstrong World 
Industries for building 
materials, and 
Acoustical Design 
Inc. for construction. 
“Hardly anyone 
wanted to tackle 
the ‘Tree at C,’ but 
we did,” says Travis 
Styer, senior project manager, Northwest 
Region, for Armstrong. “We had great 
partners in Seattle, and we all respected 
the importance of this project to the city 
and beyond. The extraordinary results are 
a testament to early planning, engineering 
and collaboration.”
TRAVIS STYER
FACTS&FIGURES 
Project: Concourse Expansion
Location: Seattle-Tacoma Int’l Airport, in WA
Concourse: C
Scope: 148,500 sq. ft. of new space over 4 floors
Noteworthy Features: Central gathering space known as 
the “Tree at C” with area for live entertainment; “Lookout at C” 
observation deck with views of airfield & Olympic Mountains
Amenities: Sensory room, interfaith prayer & meditation 
room, nursing room, pet relief area
Sustainability Features: Electrochromic glazing; solar 
panels; all-electric systems
Budget: $399 million
Funding: Airport Development Fund; future revenue bonds
Timeline: Design authorization in 2020; construction began 
mid 2023; facility opened June 11, 2026
Program Manager: Port of Seattle
Architects: The Miller Hull Partnership; Woods Bagot
General Contractor/Construction Manager: Turner 
Construction
Civil & Structural Engineering: Magnusson Klemencic 
Associates | MKA-Seattle
Mechanical, Electrical & Plumbing Engineering: 
PAE Engineers; ARUP
Ceiling/Tree Design: The Miller Hull Partnership; Woods 
Bagot
Ceiling/Tree Materials: Armstrong World Industries
Ceiling/Tree Construction: Acoustical Design Inc.
Electrochromic Glazing: SageGlass
Photovoltaic Panel Manufacturer: SolarEdge
Lighting Design: Dark Light Design