There were plenty of factors that could have forced Bismarck Airport (BIS) to shut down while crews replaced its 8,794-foot main runway: an unusually high water table, the diverse needs of five different air carriers and a construction schedule heavily influenced by funding. Despite these challenges and an early winter snowstorm, the North Dakota airport managed to remain open for traffic throughout the $64 million project. When airport officials started planning the project with engineering consultant KLJ, the FAA indicated it would need to deliver funding over three years.