65
AirportImprovement.com      May | June 2026
PARKING
GSP 
“We had 22 people from our company contribute over the 
course of the build,” she relates. “At peak construction, we 
also had a total of 150 workers on-site on a given day. In all, 
we calculated that it took 346,000 work-hours to get this 
done.” 
Since LCK was the airport’s representative, Bailey reported 
to it about the progress of work. “Hiring subcontractors was 
my company’s responsibility, but I often consulted with Scott 
[Rush] on soliciting bids and drawing up their contracts.
“We used a lot of subcontractors,” she adds. “I estimate 
that we had between 60 to 65 entities working for us during 
this project.”
In addition to its three project managers, 
Brasfield & Gorrie had several superintendents 
onsite to help manage installation. Typically, 
the company had at least four staff people 
there at any given time. “And I was there nearly 
100% of the time,” Bailey adds.
Throughout the project, she made it a 
point to keep LCK and airport management 
informed about ongoing construction and 
potential issues that could affect its progress. 
“I think that helped keep everyone on the 
same page,” Bailey reasons.
Executing a double-strand helix at two 
corners of the garage was a particular 
challenge. The design allows rental car 
customers to enter and exit in one area, while 
the general public enters and exits from a 
different spot. The separate ramps ensure 
that the two traffic streams do not intersect at 
any point. The tricky part was that the helixes 
had to join up with the main parking garage at 
each level. 
“We did a three-dimensional model of this, 
which we showed to our various workers,” 
Bailey shares. “Once the project was green-
lighted and funded, we then made a virtual 
model of this helix system, and color-coded it 
to match the schedule.”
This undoubtedly helped work stay on 
schedule throughout the two-year project. 
“We had 178 weather impact days throughout 
the 22-month construction schedule, which 
we managed without any impacts to the 
overall construction scheduled,” Bailey 
reports. “The one surprise we had involved 
weather delays due to fog. We had four 
cranes on-site, all of which were in the flight 
path of aircraft. Every morning and evening, 
we were required to notify the air traffic control 
tower for approval to raise our crane, and then 
to notify them we had completed work for 
the day. On particularly foggy mornings, we would not receive 
approval to raise our booms. In those cases, the aircraft took 
priority of the available air space until the visible conditions 
improved. This level of collaboration was necessary to ensure 
smooth and safe operations for GSP and Brasfield & Gorrie.”
 “Overall, we were lucky,” she reflects. “The winter of 2024-
2025 was fairly mild. We did not get the snow and ice that hit 
this region hard in late January and early February 2026.”
Another challenge involved adding a new exit plaza with pay 
stations very close to the old pay stations, which were later 
demolished. “We had to install a new pay station of three lanes 

View this content as a flipbook by clicking here.