14 RUNWAYS October 2026 AirportImprovement.com VNY Rebuilding 11 taxiways at Van Nuys Airport (VNY) in Southern California went well beyond replacing aging pavement. The project’s complex choreography included shortening the primary runway, a series of 80-hour closures, nighttime work, tenant relocations, weather decisions, complicated construction sequencing and funding constraints—all while keeping the active airport operating safely. And “active” is not just standard industry boilerplate. VNY, located just 15 miles north of Los Angeles International Airport (LAX), is one of the 10 busiest general aviation airports in the United States. Rebuilding From the Ground Up The $33.8 million project grew out of a straightforward need: VNY’s taxiway pavement had reached the end of its useful life. Phillip Leung, RS&H principal engineer, Aviation, and engineer of record for the project, explains that the best solution was full-depth reconstruction, plus upgrades to taxiway geometry, electrical systems, lighting and markings. The work was ultimately scheduled and completed across two years: Taxiways D, E (east and west), F (east and west) and Q in the first year, followed by C, H, M, N and P in the second. Byron Chavez, RS&H vice president and senior project manager, Aviation, says the project team worked to make the case that accepting the greater disruption of a full reconstruction up front would produce a longer-lasting result. “We knew this was going to be very impactful in one way or another,” Chavez says. “And, sure, it would be a lot quicker for us to just do a little bit of a Band-Aid patch. But then they’d have to just keep fixing it and fixing it and fixing it and fixing it.” Instead, the team advocated for taking the pavement all the way down to the subgrade and rebuilding it properly. “Our argument was that if you let us get in here and do what really needs to be done, we’ll be out of your hair for the next 20 years,” Chavez relates. Phase 1: Shortening the Runway The original plan called for the project to be treated as one large package. But because it was funded primarily with federal grants, the work had to align with two FAA grant cycles: one for 2025 and one for 2026. “Because of the timing of those FAA grants, we had to strategically prioritize which taxiways would be reconstructed during each year,” explains Laurel Soriano, the airport engineer that oversaw the VNY project for Los Angeles World Airports (LAWA). The solution was a detailed phasing plan, with the first phase of construction relying on the airport shortening its primary runway. Under normal conditions, Runway 16R is approximately 8,000 feet long. During the project, the team first shortened it to about 6,700 feet and later reduced it further, to approximately 5,824 feet, for about 30 days. The first adjustment removed the portion of runway used for takeoffs but retained the existing landing threshold and vertical instrument guidance. That allowed the Phase 1 prime contractor, Griffith, to test its paving materials on Taxiway D and get them approved before starting full production on the other taxiways. When the runway was shortened further in April 2025, the team had to make additional changes to lighting and signage and install temporary vertical guidance. Throughout this process, VNY worked to keep as many crossing taxiways open as possible so aircraft would have alternative routes to access points for the remaining runway. Van Nuys Airport Structures Major Taxiway Project to be Less Taxing on Tenants BY JENNIFER DAACK WOOLSON BYRON CHAVEZ LAUREL SORIANO PHILLIP LEUNG
View this content as a flipbook by clicking here.