57 AirportImprovement.com October 2026 AIRFIELD LIGHTING MGM building, with ADB SAFEGATE and RDI Enclosures working cooperatively and concurrently. Hutcheson Construction, the general contractor for Phase 1, was allotted 60 calendar days to complete the onsite “dirt work”—pouring the building foundation and digging paths throughout the airfield for the extensive underground electrical wiring that feeds into the building. The location of the new standalone airfield vault, just north of the air traffic control tower, was selected to enable site construction to largely occur “outside the fence.” This helped airport operations proceed with minimal interruption and also simplified the credentialling process for crew members. Undeterred by the Weather The new 800-square-foot vault was built in two separate sections that crews placed atop a custom foundation and connected onsite in January 2025. Each portion required its own wide-load semi to transport it over 750 miles from Itasca to Montgomery. One section of the structure weighed 26,000 pounds; the other part, which contained all of the electrical equipment, was nearly twice as heavy. Mother Nature was not kind to the crews that transported and erected vault. A snowstorm on the front end of the trip buried the Midwest and dropped record-breaking amounts of accumulation throughout the northern Gulf Coast. Montgomery received only 1/2 inch of wet snow, but up to 5 inches fell in surrounding counties. Because the installation site was only accessible via a gravel road, the final stretch of delivery was messy and slow. After both trucks made it to the site, crews carefully lifted each section of the building into place using forklifts and a crane. Electrical connections were then established. “We had to rough in all the electrical and make sure we hit pre-cut holes in the floor,” recalls Paul Hutcheson, owner of Hutcheson Construction. “It was a huge challenge. “We worked off drawings that showed exactly what the building was going to look like,” he continues. “As long as that building showed up the way the drawings said it would, we were OK. We had pockets in the floor that were 6-by-18 inches, and we had to get six 2-inch conduits to land perfectly in the middle of a field with nothing to go off of and make sure it all married up.” Crews worked through the bitterly cold January night to make it happen. Rewiring the Field, Updating Lights With the new vault complete, work began on Phase 2, the airfield cabling, signage and lighting replacement. Onsite work for Phase 2 started in March 2026 and is expected culminate in spring 2027 with a final changeover to the new electrical vault. “Our challenge in Phase 2 was to find a way to keep the existing lighting system active during the day with the airport open while we built the new one,” says Matt Thomason, Alabama aviation leader for Goodwyn Mills Cawood. That included minimizing airfield construction traffic to avoid disrupting MGM’s ongoing commercial service, general aviation traffic and military operations associated with the 187th Fighter Wing of the Alabama Air National Guard. “When we switch over from one electrical vault to the other, it must be a literal flip of the switch to avoid closure,” Thomason emphasizes. To satisfy FAA requirements on spacing and layout, Goodwyn Mills Cawood staggered the location of the new system within FAA guidelines as to not interfere with the active system. “Care was taken at every step to ensure clear visibility to the active system for pilots to maintain their situational awareness,” says Thomason. “For the runway lighting, we utilized a ‘trunk and branch’ method for the new copper cabling,” he explains. “The trunk line was positioned outside the runway safety area (RSA) so as to not require shutdown of the runway during daytime construction. Branch lines come into the RSA off the trunk line to connect to the edge lighting fixtures. This enabled minimal shutdown except for the work inside the RSA. We reduced the runway closure to overnights only with minimal impacts on the airport’s users.” Access for future maintenance was also a key consideration. “At every branch/trunk intersection, we have a three-way junction can to pull wire and perform splices as necessary for both construction and facilitating long-term maintenance,” Thomason details. “For areas outside the runway, we utilized a detailed phasing plan to enable operations to fully continue on the taxiway/ apron network while allowing the contractor to close sections for daytime work.” MATT THOMASON PAUL HUTCHESON
View this content as a flipbook by clicking here.