61
AirportImprovement.com      October 2026
ENVIRONMENTAL 
FAR
Jeff Klein, project manager with Mead 
& Hunt, notes that all runoff is directed 
to the same inlet throughout the year. 
When aircraft are not being deiced and 
glycol isn’t an issue, the airport can open 
diversion valves so runoff is discharged 
into the storm sewer system. When aircraft 
deicing fluid is being sprayed during winter, 
valves are changed to direct all runoff to 
the deicing runoff collection system, where 
it is pretreated before ultimately getting 
pumped to municipal treatment lagoons 
located north of the airport.
Going Underground
Construction of the new underground 
storage and piping system began in 
September 2024 and was completed last 
fall. Installation of the pumping station that 
transports stormwater and deicing runoff 
to the city’s nearby treatment lagoons was 
completed this summer. 
The project cost $13.78 million, with 
90% funding from Airport Improvement 
Program and discretionary grants. The 
remaining 10% of the cost was split 
between state and local sources. 
Engineers from Mead & Hunt worked 
closely with city engineers when 
excavating through a crucial levy to install 
the needed piping. The elevated earthen 
levy protects the lagoons from overland 
flooding and helps prevent wastewater 
from leaking onto adjacent property. 
 “Excavating through this certified levy 
was a challenge due to the compaction 
standards necessary to make certain the 
levy maintained the required certification,” 
Dobberstein notes. “The city was great to 
work with on this aspect of the project.”  
Getting Started
Airport officials and the project team 
considered multiple strategies, including 
the option to continue hauling away spent 
deicing runoff, before settling on Mead & 
Hunt’s system for underground storage and 
controlled release to the sanitary system. 
The airport had already installed similar 
infrastructure adjacent to the original terminal 
apron and cargo apron, notes Dobberstein. 
The first two phases of the recent 
project addressed FAR’s increased 
stormwater runoff volume resulting from 
the increased amount of pavement. 
Aluminized corrugated metal pipe from 
Contech Engineered Solutions was 
buried in two greenfield areas: one north 
of the terminal, another to the east. One 
detention system required 1,512 linear 
feet of 66-inch pipe. The second used 
771 feet of 96-inch pipe. 

View this content as a flipbook by clicking here.