41
AirportImprovement.com      July | August 2026
BAGGAGE 
BWI
Design work on the project resumed 
in January 2021, but with a significant 
change in budget and direction: The 
basement concept was scrapped, the 
system had to be located entirely at 
ground level and the overall project 
budget was cut by $100 million. 
New Budget, New Baggage
Much of the cost BWI was able to trim 
came from the redesign (times three) of the 
baggage handling system. The first design 
was a “base design” to identify/clarify what 
would be built, and the second was a value-
engineered version of it that the airport used 
for contract negotiations. Subsequent design 
changes moved much of the baggage 
handling system design construction into the 
new expansion area, which was unavailable 
during earlier design efforts.
“So we then subjected [blended] 
our value-engineered design with their 
recommended solution, shuffled the cards 
together and ended up with the best 
value,” says Shank. 
He notes that early involvement from 
Siemens, the baggage handling system 
contractor, was a significant benefit during 
the Construction Manager at Risk project 
because its specialized knowledge brought 
additional efficiency and helped reduce the 
overall cost. While this was the first project 
BWI used the Construction Manager at 
Risk delivery method for, it will not be 
the last, Shank remarks. The effect on 
collaboration, partnering, schedule and 
budget left a very positive impression.
“We continuously value engineer. We 
don’t just do it once and we’re done,” 
Shank emphasizes. “Because as you go 
along, there might be something that’s an 
improvement over your original concept.” 
Eliminating the basement and 
simplifying the building’s geometry for 
cost and schedule efficiency resulted 
in a streamlined, rectilinear connector 
between concourses A and B. 
With a shorter overall connector facility, 
the baggage handling system was resized 
(to about 1.5 miles long with 670 motors) 
FACTS&FIGURES 
Project: New Baggage Handling System 
Location: Baltimore/Washington Int’l Thurgood Marshall 
Airport
Installation Site: New Concourse A/B Connector 
Cost: Part of $520 million budget that also includes 
concourse connector
Funding: Airport revenue bonds ($330 million); 
MD Transportation Trust Fund; Airport Improvement 
Program grant
System Size: More than 1.5 miles long with 670 
motors, 7 EDS machines (plus room for 1 more), 6 new 
claim carousels
Capacity: 3,255 bags/hour 
System Features: 2 domestic transfer drop-off 
positions; 1 int’l recheck drop-off position; 2 independent 
sortation lines with bypass encoding stations; additional 
outbound bag makeup operations; redundant power 
Ramp-Level Features: Consolidated operations, 
locker rooms & management facilities for Southwest; 
dedicated entry for badged staff; automated passenger 
exit technology; additional substation for power 
redundancy; storage, receiving & trash removal facilities 
for new concessions in connector; dedicated concessions 
service elevator; improved inbound tug operations; 
unrestricted vehicle service road
Prime Designer/Engineer: Jacobs
Baggage System Design Oversight & TSA 
Coordination: Studdiford Technical Solutions LLC
Baggage Handling System Designer: VTC 
Architect of Record: The Sheward Partnership LLC
Concept Architect: Abstract Group Inc.
Civil: Airport Design Consultants Inc.
Mechanical, Plumbing: JMT
Geotechnical Engineer: Robert B. Balter Company
Program Manager: AECOM
Construction Manager at Risk: Clark Construction
Construction Manager/Inspection for Site 
Prep: Parsons
Construction Manager/Inspection for Baggage 
System: WSP
Baggage System Contractor: Siemens 
(Vanderlande Logistics)
Explosives Detection Machines: Leidos
Gear Motors: NORD  
Electrical/Power Supplier: Curtis Power Solutions
Security Installation: M.C. Dean
Baggage Handling System Electrical: Hatzel 
Buehler
Electrical Installation: Freestate Baltimore
Lighting Components: GVA Lighting (via Alliance 
Lighting); Gammalux Lighting

View this content as a flipbook by clicking here.