42
ENVIRONMENTAL  
November | December 2026      AirportImprovement.com
TPA
The location of Tampa 
International Airport (TPA) is both 
a blessing and a curse. Being near 
the upper shore of Tampa Bay provides 
sought-after views and a convenient 
location in the middle of the Tampa Bay 
region. By the same token, though, it also 
puts the airport at risk for flooding and other 
damage when extreme weather moves up 
Florida’s Gulf Coast.
When Hurricane 
Milton hit the Tampa 
area in 2024, TPA 
officials were dismayed 
by how much water 
breached the airfield. 
“We saw the bay 
get to the highest 
levels we’d seen in quite a long time,” 
remembers TPA Construction Director Dan 
Seeley. “Floodwaters approached the west 
airfield, the section near the bay, and we’d 
never seen that.” 
While TPA was anything but flatfooted 
when Milton hit, having water on the airfield 
highlighted the region’s severe storms and 
revved up management’s long-term efforts 
to adapt to changing climate conditions. 
Personnel immediately reassessed the 
vulnerability of crucial airport infrastructure, 
particularly two airfield electrical vaults 
beside the Aircraft Rescue and Firefighting 
Station. Although the vaults have never 
flooded, waters associated with Hurricane 
Milton came too close for comfort. 
For TPA, the major issue was torrential 
rains—more than 11 inches in just a few 
hours. The event “opened our eyes to sea 
level rise, storm surge and that things have 
changed,” Seeley says. “Older [weather] 
models didn’t reflect what the environment 
was doing now.” 
In the aftermath of any storm, keeping 
the airfield lights operating is crucial to 
keeping the airport operating and aiding 
recovery efforts. Electrical vaults protect 
the equipment that powers the airfield, 
therefore TPA officials were intent on 
protecting them. 
To do so without adding significant 
permanent infrastructure, the airport 
Tampa Int’l Adds Deployable Floodwall 
to its Storm Prep Options BY SCOTT BERMAN
DAN SEELEY
FACTS&FIGURES 
Project: Protecting Airfield Electrical Vaults 
Strategy: Deployable flood barrier
Location: Tampa Int’l Airport, in FL
Cost: $1.9 million
Funding: Airport capital funds; $55,177 Airport 
Improvement Program grant
Product: Clima Armour FloodWall, from AquaFence
Size: 9 ft. tall; 150 panels
Construction & Maintenance: H.L. Pruitt Corp.
Product Purchased: Aug. 2025
Related Construction: Early Aug. 2026 to early 
Sept. 2026
Climate Change Resilience Assessment 
& Modelling: 2019, by RS&H
Key Benefits: Protecting key assets that support 
operational continuity; system can be removed from 
storage & assembled in hours when major storms are 
predicted 

View this content as a flipbook by clicking here.