b'BAGGAGE WWMCO 23FACTS&FIGURES Project: New Baggage Handling SystemLocation: Orlando (FL) Intl AirportSite: South Terminal ComplexAirport Operator: Greater Orlando Aviation Authority Cost: $130 million Design: 9 monthsEngineering: 10 monthsSupply: 12 monthsInstallation: 18 monthsCommissioning: 15 monthsTesting: 12 monthsSouth Terminal Concept Architect: FentressSouth Terminal Architect of Record: HNTBSouth Terminal Construction: Hensel Phelps; Turner-Kiewet Construction Co.Baggage Handling System Design & Construction: VanderlandeVariable Frequency Drive Motors: NordBaggage System Maintenance & Operation: VanderlandeTechnology Consulting: JSM & Associates Owners Rep for Design & Construction Oversight: JSM & AssociatesSystem Features: Individual carriers/totes for each item; upper-level baggage claim area; storage facility for bags checked in early Key Benefits of Tote System: High-capacity, high-speed baggage handling; fewer mishandled bags; shorter connection times; low energy consumption; reduced noise; bag jams virtually eliminated; bag slides increase accuracy of makeup AirportImprovement.comMay | June 2022'