b'70 LAS FUELING FACTS&FIGURES Project: Fuel PipelineAirports Served: Harry Reid Intl; Henderson Executive; Jean Sport Aviation Center; North Las Vegas Airport; Perkins FieldLength: 3.5 milesAssociated Improvements: New storage tanks & upgraded infrastructurePhase I: $30 million for 65,000-barrel tank, improved system controls & larger electrical buildingPhase II: $40 million for trio of 100,000-barrel replacement tanks, new pump filtration system & new load rack and pipelineNew Storage Capacity: 502,134 barrels (enough fuel for 18.5 days of operations)Project Timeline: Planning began in 2005, Phase I construction completed in 2011; new pipeline operational in March 2022System Owner: LASFuel airline consortiumConstruction Manager: Argus Consulting Operator: Swissport Fueling ServicesGeneral contractors: New-Com Inc.MMC- ACME Electrical Engineering Facilities & Pipeline: Spec Services Inc. Engineering & Permitting: TY Lin Public Outreach (Pipeline ROW):GC Garcia Key Benefit: Increased on-airport fuel storage & throughput capacityMay | June 2022AirportImprovement.com'