b'TERMINALSYVR 9FACTS&FIGURES Project: Terminal ExpansionLocation: Vancouver Intl AirportStrategy: Expanding Pier D to accommodate more intl trafficSize: 226,042 sq. ft.Cost: $220 million (U.S.)Funding: Capital, debentures & airport improvement feesConstruction: Dec. 2017Jan. 2021Key Components: 8 new international gates; 4 contact gate holdrooms; 4 remote stand operations holdrooms; glass-enclosed open-air atrium; new concessions; additional seating & lounge areas; yoga studio; multi-faith prayer room; quiet room; immersive digital displays; 2 childrens play areas; enhanced restroom designsPrime Architect: Kasian Architecture Interior Design & Planning Ltd.Structural Engineering: Bush, Bohlman & PartnersMechanical & Plumbing Engineering/Design:Integral Group Inc. Sustainability/Energy Modeling & Fire Suppression:Integral Group Inc. Electrical, IT & Lighting Design: WSP Group PHOTO: VANCOUVER AIRPORT AUTHORITY Landscape Architect: Connect Landscape Architecturetemporary boarding bridge to allow YVRinternational flightsparticularly fromCivil Engineering: Hatch Engineeringto service its airline partners with anChina and other parts of Asia.Construction Contractor: PCL Constructors Westcoast Inc.additional gate that would have otherwiseThe new facility is a large steel momentCode Compliance: LMDG Building Code Consultants Ltd. been unavailable during construction. frame structure with three suspendedGeotech: Thurber Engineering Ltd. With the project on track to end inlevels. Mechanical and electrical servicesCommunication & Security Systems: WSP GroupMay 2020, YVR stopped constructionare located on the top level; passengerBoarding Bridges: JBT AeroTechin March 2020 due to COVID-19. Wecirculation areas are on the lower twoDigital Displays: EOS Lightmediawere one of the fewlevels. Contractors installed 18,000 steel airports that actuallybeams weighing almost 10 million poundsDigital Content: Creacom Services Inc.paused construction,to create the structure. The buildingSteel Fabricator: Whitemud Ironworks Ltd.remarks Vancouveris designed for Code E and F aircraft,Castings: Castconnex Airport Authorityproviding ample space between gates toSubcontractors: Combined Painting; Division 15 Mechanical; Architect Nancyaccommodate wingspans; and holdroomsFlynn Roofing; Island Precision Architectural Millwork; Jacob Stern. After aare large enough for the associatedBrothers; Protect Electric; Robertson Drywall; Flynn Roofing; three-month pause,passenger loads, notes Andy Metten,Benton & Overbury; Holland Landscaping; Paladin Technologies; NANCY STERN Apex Granite & Tile; Crosstown Metals; Fast Track Floors; Fujitec construction resumedpartner and structural engineer at Bush,Elevators; ESC Automation; Tight 5 Insulation; Knight Signsin June 2020 with strict COVID protocolsBohlman & Partners. The apron level in place. At the height of construction,houses airline maintenance offices, tenantLighting Suppliers: Acuity; Alights; Cree; Lumenpulse; Selux; there were more than 500 workersstorage, service rooms and the newErco, ETC; Ledalite; Deltalight; Neoray; GE Ltg Controlsinvolved with the project. The facilityremote stand operations. Electrical Equipment: Schneider Electricwas handed over to YVR Operations inIntegral Groups mechanical systemHoldroom Seating: Arconas January 2021, but the Airport Authorityneeded to tie into the existing heatingSoft Seating: Arcadia; Cape Furniture; Chairs 101; Global did not open the new part of the buildingand cooling plant. The design createdFurniture Group; Kusch; Sadler Vitra Verpanuntil June 2022 due to a decrease innew pumping nodes within an existingFood Court Table Tops: ChopValueTables with Charging Units/Power & Stools: Arconas AirportImprovement.comJanuary | February 2023'