b'52 PAH TERMINALSFACTS&FIGURES Project: New TerminalLocation: Barkley Regional AirportWest Paducah, KYTerminal Size: 26,000 sq. ft.Approx. Cost: $43.5 millionFunding: $20 million in FAA AIP Terminal Discretionary Grants; $10.8 million in FAA AIP Airside Discretionary & Entitlements Grants; $850,000 from CARES Act (via FAA AIP); $1.15 million from American Rescue Plan Act (via FAA AIP); $5 million from Kentucky Dept. of Aviation; $5.7 million combined from city of Paducah & McCracken County; $80,000 from Paducah Area Community Reuse OrganizationConstruction: Nov. 2020June 2023Key Components: ADA-compliant features; mothers room & family restrooms; upgraded security systems; private TSA screening room; TSA on-site office space; digital monitors; automated baggage handling system; passenger boarding bridge; passenger, employee & car rental parking lots; newBarkley Regional Replaces entrance road; new terminal apronLead Aviation Planner & Architect: AlliianceLocal Architectural Partner: PFGW Outdated Terminal With New Terminal Building General Contractor: MP Lawson Construction Inc. Facility Packed With UpgradesSite Improvements General Contractor: Jim Smith Contracting Co. LLCBY KRISTEN RINDFLEISCHCivil Engineering, Grant Administration & Budgeting Support: CHA Consulting Inc. This June, Barkley Regionalterminal was more Site Survey & Geotechnical Investigation: AmericanAirport (PAH) in West Paducah,than 65 years old and Engineers Inc. KY, completed a curb-to-tarmacwas proving costly Structural Engineering: BFW Engineering & Testing Inc. transformation. In addition to building ato maintain. Its boiler Electrical Engineering: Marcum Engineering LLC new terminal, the airport constructed asystem had failed new entrance road, brought in brand-newtwice, there was Art Consultant: Via Partnership utilities, added new parking facilities andasbestos in some Telecom & Security: Faith Group built a new terminal apron with a passengerparts of the building, DENNIS ROULEAUFull-Body CT Scanner: Analogic boarding bridge. Its newly constructedand the several dated Baggage Handling System & Passenger Boarding26,000-square-foot terminal is more thanHVAC units needed frequent repair. In Bridge Engineering: Swanson Rinktwice the size of the facility it replaced and2011, Barkley Regional Airport Authority Passenger Boarding Bridge: JBT is filled with updated features such as ADA- (BRAA) commissioned a terminal siting Automated Baggage Handling System: ASI compliant restrooms, a more advancedand footprint study. baggage handling system and upgradedAtkins, the firm that conducted the Seating: Arconas; Martin Brattrud; Davis; Keilhauer security. Moreover, all passengers now Wayfinding: Entro board through an enclosed jet bridge ratherstudy, recommended building a new terminal on a greenfield site in the south-Terminal Siting & Footprint Study: Atkins than outside from the ramp. central portion of the airports property. Key Benefits: Improved passenger experience &Airport Executive Director DennisIn 2018, BRAA validated the 2011 study operational efficiencies; room for expansion & increasedRouleau explains that PAHs previousto confirm the proposed terminal size capacitySeptember 2023AirportImprovement.com'